“In advance of the first public meeting on the project, scheduled for Thursday night, the wish list for the project and accompanying free land is as wide-ranging as it is lengthy: A network of world-class bike and walking paths. A Harvard campus expansion. Thousands of new housing units. A Boston Marathon memorial pedestrian overpass. A hulking Olympic stadium. A new West Station that could provide a rapid transit rail link between Allston and Cambridge.” – excerpt from Plans for straightening Mass. Pike stir expansive visions, article by Martine Powers, Boston Globe, 4/10/2014. Photo by Jonathan Wiggs / Globe Staff.
FULL ARTICLE: http://www.bostonglobe.com/metro/2014/04/09/highway-project-holds-promise-for-revamped-region/2lCX89t55FWnHWSxmZe2xM/story.html
Comments on Charles River Basin Connectivity Study
December 16, 2013
Richard K. Sullivan, Jr.
Executive Office of Energy and Environmental Affairs
Attn: Dan Driscoll
100 Cambridge St., Suite 900
Boston MA 02114
RE: Comments on the Charles River Basin Connectivity Study
Dear Secretary Sullivan:
WalkBoston has reviewed the Charles River Basin Pedestrian and Bicycle Study for Pathways and Bridges, the so-called Connectivity Study. Our comments arise from the document and from the recent presentation of the study to the public.
The Connectivity Study is very exciting work, as it assembles the issues of movement along the basin very effectively, and points out the possibilities for positive changes in the paths, walkways and running facilities along the River. DCR should be very proud of this feat, and should proceed into implementation of priority aspects of the planning effort as soon as possible.
We were particularly heartened by the Study’s general recommendations for the Basin: “DCR should strive to develop a 10’-wide paved path with a parallel soft-surface trail or shoulder for runners (emphasis added) where possible….. In “pinch point” conditions, a minimum 8’ paved path, with 3’ shoulder on one side, should be incorporated.”
This acceptance of separate paths for runners and joggers – and also pedestrians – is a very important aspect of the planning and represents continuity with past planning efforts.
In the 2002 Master Plan for the Basin a stated goal was to provide safe and continuous bicycle, skating, and pedestrian access along the entire length of the Basin, with a “separation of footpaths and bike paths where doing so will not create excessive pavement near the shoreline.” The master plan also called for reducing congestion and minimizing conflicts on the paths (presumably conflicts between bicycles and pedestrians).
In 2005, users were surveyed to discern attitudes about the river facilities. The survey asked respondents to list and rank how they used the Basin. The top twelve responses were, in order of frequency:
• Walking for pleasure
• Attending concerts or events
• Relaxing in the park
• Driving on the parkways
• Running or walking for exercise
• Biking
• Using Riverbend Park in summer
• Picnicking
• Enjoying the outdoors with children
• Inline skating
• Walkathons
• Informal sports
More than sixty percent of those surveyed used the Basin more than once a week for strolling, relaxing, attending concerts or attending special events. Eighty-six percent asked for easier and safer pedestrian access to the Basin, and an equal proportion recommended separating pathways by user types. Users also frequently called for more benches and places to sit, more wildlife areas, more park rangers, and more convenient parking.
If the Continuity Study can be regarded as an update to the Master Plan, we think it may be leaving out some of the emphasis that the authors of the two planning documents clearly stated. In particular, the separation of bicycle and pedestrian paths does not seem to be as important an aspect of the plan as the users of the park suggested to be of high importance. WalkBoston believes that path separation should be integral to all elements of the plan, as it will help deal with the many problems inherent in an area that is so heavily used with so many potential conflicts between users.
We urge consideration of the following:
1. The elimination of conflicts between users of the paths should be uppermost as a safety precaution. Conflicts arise where bicycle traffic is moving rapidly through areas where pedestrians are strolling, causing dangerous situations for all. The conflicts are particularly difficult for commuting cyclists, some of whom are loath to slow down.
2. An expansion of the definition of ‘multi-use path’ would open options that are not clearly included at the moment. Multi-use pathways in the Basin should have an element – probably a parallel, separate path – that would cater to slow-moving walkers, runners and joggers. The foot traffic path could be built entirely separated from the paved path or built as a non-cambered shoulder.
3. Multi-use paths are appropriate for areas where there is low density of use by walkers, runners and cyclists, but should not dominate planning for the heart of the very heavily used park system in the center of Boston. Instead, the overriding goal should be provision of facilities in which space is plentiful for all park users and potential conflicts between users are minimized using methods that are appropriate to each location.
4. Existing multi-use paths should be expanded all along the river to meet the definition of separation between paths based on user needs.
5. Recognition of what runners and joggers show about their desires for facilities would help in planning new paths. Narrow dirt paths that exist informally alongside many of the paved paths in the Basin demonstrate a clear desire for a softer surface preferred by runners. The softer surfaces can also be used by pedestrians and will clearly help separate cyclists from people on foot.
6. A demonstration of the path separation is included in the proposal for the Greenough Boulevard narrowing. The effects on users would be an important element to explore.
7. Path separation in the near term may only be possible on one side of the river. The Greenough Boulevard proposal and the Memorial Drive narrowing between the Eliot and Anderson Bridges point in the direction of path separation as a major feature on the north bank. Continuation of path separation both west and east of these two segments would be a next logical step. Except at intersections, parkland seems to be available for new or modified paths.
8. An unfortunate aspect of all path planning along the river is the intersections with streets at the bridges. The narrow paths that exist at many of the bridges will be a major feature of riverfront paths for a long time, but should not preclude path separation away from the bridge intersections.
9. As long-term improvements, underpasses at bridge intersections are appropriate and important options that will enhance the recreational and transportation options for many Basin users.
We appreciate your consideration of our comments and look forward to your responses to them. Please feel free to contact WalkBoston with questions you may have.
Sincerely,
Wendy Landman Bob Sloane
Executive Director Senior Project Manager
Cc Nicole Freedman, Boston Bikes
Cara Seiderman, City of Cambridge
Steve McLaughlin, MassDOT
Margo Levine Newman, The Esplanade Association
Renata von Tscharner, Charles River Conservancy
Herb Nolan, Solomon Fund
Jackie Douglas, LivableStreets Alliance
Pete Stidman, Boston Cyclists Union
David Watson, MassBike
Tom Grilk, Boston Athletic Association
Comments on the DEIR for The Boston Garden, MEPA #15052
November 8, 2013
Secretary Richard K. Sullivan, Jr.
Executive Office of Energy and Environmental Affairs (EEA)
Attn: Alex Strysky
100 Cambridge Street, Suite 900
Boston MA 02114
Commissioner Thomas Tinlin
Boston Transportation Department
One City Hall Plaza
Boston, MA 02201
RE: Comments on the DEIR for The Boston Garden, MEPA #15052
Dear Secretary Sullivan and Commissioner Tinlin:
WalkBoston has reviewed the DEIR for the Boston Garden project. The proposal will improve the second largest pedestrian, transit and commuter rail interchange locations in the city. From WalkBoston’s perspective, one of project’s key challenges is handling the many daily pedestrian trips generated by subway and commuter rail riders, on-site workers and residents, and the large crowds generated by the TD Garden Arena.
The design of the 2.8 acre site includes a large office building, a hotel and a substantial residential building, comprising 1,870,000 square feet of new structure. The basement and first two levels of the building are predominantly retail. A lower level garage expands the existing below-grade parking facility by 800 spaces, for a total of 2075 in the complex.
The magnitude and importance of pedestrian access has prompted a number of comments and questions about the ways in which the proposed plan meets the needs of walkers both to and within the site. It is very important to distinguish between the site design, which is under the control of the developer, and the design of Causeway Street, which is under the control of the City. We believe that these two components must be designed to work well together, and our comments address both areas because it is not possible to separate them from a pedestrian perspective. For that reason we have addressed our comment letter to both MEPA and the City of Boston Transportation Department.
CONFUSION ABOUT PEDESTRIAN CROSSINGS OF CAUSEWAY STREET
The DEIR includes a design for Causeway Street that has been superseded because of the City’s receipt of a federal TIGER grant that will pay for the reconstruction of the street. As described to WalkBoston by several City staff members, the designs shown in the document are currently being modified by the City to incorporate cycle tracks instead of bicycle lanes and to possibly alter original alignments of lanes on the street. New designs will change the approved 25% design drawings for all pedestrian crossings on Causeway Street, and for vehicular accommodations on the street as well. The details of the proposed changes have not yet been shared, and WalkBoston will actively participate in review of the new design once it is presented. Rather than provide comments on the current design we have focused this letter on suggestions about elements we would like to see in the new design.
MAJOR PEDESTRIAN ISSUES
1. Projected pedestrian volumes into and out of the site exceed vehicular volumes.
The number of people who currently enter the rail and arena adjacent to the site is impressive. Per the MBTA Blue Book, there are 26,763 weekday commuter rail boardings at North Station, and 16,702 weekday entries into the Green and Orange Lines. In addition many more people use the transit lines, streets and sidewalks when an event is scheduled in the 19,000 seat TD Garden. North Station is the 2nd busiest transit station in the MBTA system (exceeded only by South Station). Causeway Street carried 14,800 vehicles per day in 2009, according to MassDOT.
2. Pedestrian crossings of Causeway Street are one of the most important issues to be explored.
a. Canal Street is the major pedestrian approach to the site.
Reflecting the significant anticipated growth in transit and pedestrian trips, a new pedestrian entrance to both the rail station concourse and the TD Garden is planned for the location where pedestrians will cross Causeway Street from Canal Street. Historically Canal Street served as the pedestrian route to North Station from the Downtown financial and retail districts, and in the planned design it will regain that prominence (Fig. 1-14.)
Walking along Canal Street is fostered by wide sidewalks and by the street’s slow speed, narrow travel lanes, corner bulb-outs and traffic signal designs. Pedestrians are encouraged to follow a walking route along Congress Street from the financial district and up Canal Street to North Station.
Retail property uses along the frontage of Canal Street have also changed over time and it now includes many uses catering to people attending sports events including bars and restaurants with large outdoor seating areas.
The private and public expenditures on Canal Street have emphasized it as the primary walking route, thus leaving Friend, Portland and Haverhill Streets much less used by walkers.
b. The design of the Canal Street entrance emphasizes its importance
“Champions Way,” is the grand entrance into the project from Causeway Street – directly aligned with Canal Street. It is approximately 50’ x 200’ (10,000 square feet), sized to handle large numbers of people accessing the site and lined with retail facilities to attract walkers. (Nothing of this nature is proposed for either the Friend Street or Haverhill Street approaches.)
About half of Champions Way will be open to the sky, and at the far end, near the rail concourse, is a ‘mixing bowl,’ where the entrance is divided into three parts leading to the Commuter Rail Station, the second-floor TD Garden and the below grade North Station subway station.
Interestingly, the proposed Champions Way has roughly the same dimensions as the Channel Gardens/Promenade leading into New York’s Rockefeller Center. The New York example spreads out into wide sidewalks at either end of the Promenade; here, that would be somewhat comparable to the wide sidewalk along Causeway Street and the expanse of the rail station concourse at the opposite end of the entrance court.
Other local comparisons are also apt. The Canal Street entrance is about one-half the length and roughly the same width as Yawkey Way, used as a pedestrian street for access to the 40,000-seat Fenway Park. South Station’s main entrance has roughly 6,500 square feet divided into two walkways and a row of escalators and small shops. The South Station vestibule also connects with relatively large open areas on both ends, a triangle of sidewalk in front of the station is about 9,300 square feet and a plaza for pedestrians on the opposite side of the street is an additional 17,500 square feet.
c. The new entrance to the site is more than a replacement of existing site entrances.
Walkers currently enter the TD Garden and rail station concourse via east doors facing the sidewalk along Legends Way and west doors facing the O’Neill Building path. This layout is reflected in current pedestrian access patterns with existing peak hour pedestrian traffic heaviest where Friend Street crosses Causeway Street, as commuters walk toward the western doors. The same pattern does not exist at the intersection of Haverhill and Causeway Streets, perhaps because walkers heading to the east entrance use the MBTA’s underground passage beneath Haverhill Street. Once the proposed new development is in place, the importance of the east and west entrances will diminish significantly and the new entrance at Canal Street will be the focus.
3. Projections of pedestrian activity on parallel streets do not seem to reflect the current design. Causeway Street intersects with four streets in front of the project site – Portland, Friend, Canal and Haverhill, and the distance between the streets is quite narrow. The intersections of Portland, Friend and Canal are three-way, and Haverhill St. is a four-way intersection. All have at least one crosswalk, and there are signals at Haverhill and Portland Streets. A brief analysis of each street is useful to explore their role in the pedestrian network leading to North Station. As noted above, Canal Street is the primary pedestrian route and the other streets have narrower sidewalks, fewer retail outlets catering to Garden event patrons, and more parking lots that reduce the quality of the pedestrian experience.
- Portland Street, slightly west of the project site, serves relatively few pedestrians. Most walkers on this street may be heading toward the O’Neill Federal Building at the corner of Causeway and Merrimac Streets, and some may be heading toward the west entrance to the TD Garden and the rail station concourse, although the walking route is not direct.
- Friend Street provided a more direct route to the west entrance of the TD Garden/Rail Station, but it crosses Causeway Street at a location that does not align with the O’Neill Building pathway, and the existing diagonal path across the project site will disappear with the new development.
- Haverhill Street provides access to the Orange Line/Green Line station, and both sides of this 2-block street have been recently developed with large apartment buildings. However, many loading zones for the new buildings and vehicular entrances make the street less pedestrian-friendly than Canal Street.
4. Pedestrian volume projections may need re-examination.
Existing and projected pedestrian volumes for the four street crossings are provided in the document. Existing pedestrian volumes are highest in the weekday AM peak hour at Portland Street which would seem to stem from Commuter Rail passengers walking from North Station, exiting via the west door and walking toward downtown.
In future projections for the 2017 Phase I development, all pedestrian movements grow, but the largest growth is projected for Friend and Haverhill Sts. which lead only to the east and west entrances to the building. Canal Street traffic grows somewhat, but Haverhill Street projections for the AM peak hour grow to be 10 times larger than the existing pedestrian movement at that intersection. It is unclear if these volumes reflect a route using Haverhill Street’s underpass beneath Causeway St. and the sidewalk along Legends’ Way leading to the east doors of the rail station and the TD Garden. It seems unlikely that such high volumes could cross Causeway St. safely at grade.
For the 2028 full-build, pedestrian volumes grow again, but the pattern is difficult to understand: pedestrian numbers increase substantially at both Friend and Haverhill Sts., but change very little for Canal Street, despite the design’s clear emphasis on the new entrance focused on the traditional walking path from Downtown to North Station.
By contrast, vehicular traffic through the four intersections changes very little from existing levels, declines slightly for the 2017 Phase I, and rises again for the 2028 full-build.
We are puzzled by the projections and request that the proponent describe the volumes and their projected locations in detail.
5. The traffic signal program for Causeway Street needs re-examination.
If this development is to focus its principal entrance on Canal Street, and pedestrian traffic at that location is to increase, the intersection of Causeway and Canal Streets must be signalized for pedestrian safety. The DEIR deliberately fosters jaywalking at both Canal and Friend Streets: a logic of unsignalized intersections is stated in the report: “The unsignalized crossings of Causeway Street at both Friend Street and Canal Street operate at a pedestrian LOS F during the peak hours independent of the full build-out of the Project. Again, under actual operating conditions, pedestrians cross these locations in a platoon when a gap in traffic is afforded in at least one direction on Causeway Street thereby resulting in less pedestrian delay than predicted by the analysis model.”(DEIR page ES-7; pages 3-2 & 3-4; table ES-4)
PROPOSED SOLUTIONS
WalkBoston is excited about the pedestrian service this project will provide. To make the project more appealing and safe for walkers, we suggest the following steps that would more clearly recognize the important role of pedestrians in accessing this site:
THE CAUSEWAY STREET FRONTAGE OF THE SITE
1. Propose a hierarchy of pedestrian crossings on Causeway Street. Canal Street will be the most important pedestrian crossing of Causeway Street (on ground level) based on this design. Haverhill Street is the most important pedestrian crossing of Causeway Street (that passes underground) based on this design. Friend and Portland Sts. will be relatively lowvolume pedestrian crossings.
2. Think of Canal and Haverhill Sts. (and possibly Friend St. as one intersection to aid in finding pedestrian solutions. The block front distance between Haverhill Street and Canal Street is manageably short (about 120 feet). Friend St. is a bit further away from Canal St.
3. Signalize Canal/Haverhill Street at Causeway Street as a single coordinated traffic intersection. Portland St. could also readily be signalized. Friend St. does not necessarily need a traffic signal, if alternative pedestrian crossing locations can be encouraged and if sidewalk and street crossing designs discourage pedestrians from crossing at this location.
4. Build a level pedestrian crossing table for this intersection to slow traffic from both directions. The table should extend a total of at least 200’ from the MBTA headhouse area at Haverhill and Causeway Sts. to the west side of the intersection of Canal and Causeway Sts.
5. Try to attach Friend Street to this raised crossing, recognizing there will be some difficulties. Canal, Friend and Haverhill Sts. constitute the majority of pedestrian crossings 5 on Causeway St. and thus may be considered as a single unified crossing location. Friend Street might be included in the raised table, but issues arise. First, extending the platform to Friend Street doubles its length, potentially leading to the use of the street for storage of vehicles at signals that may interfere with large-volume pedestrian crossings. Second, an additional signal at Friend St. so close to the Canal/Haverhill signals complicates the vehicular signal patterns for the whole street. Third, much of the proposed truck service traffic into the site is located at a door between Friend and Canal Streets, perhaps causing conflicts with surface gradients of the proposed raised platform and adding turning movements into a pedestrian facility. Entrances and exits into this truck service area should take place only from westbound Causeway Street – thus, no left turns for eastbound access.
6. Permit no left turns to or from Causeway Street. Both Causeway Street westbound and Haverhill Street northbound can become vehicular entrances into the site’s parking garage, but exiting traffic from this ramp should only be permitted to turn left to find its way to the Central Artery or Keaney Square. Traffic exiting here and wanting to turn right should be encouraged to use the existing exit ramps at the rear of the building, where Nashua Street provides direct access to Storrow Drive, Route 28, and the entrances to the Central Artery bridge and tunnels.
7. Design the cycle track proposed for Causeway St. to minimize impacts on pedestrians. The alignment of cycle tracks should not interfere with pedestrian movement. Cycle tracks could be located in space where landscaping is proposed. Cycle tracks should be located together so that pedestrians know where to expect bicycles. Pedestrians should be informed of the existence of the cycle tracks through a combination of eye-level signs and painted warnings on the pavement. Bicycle signals and signs in both directions should be installed to warn of pedestrian crossings. Bicycles waiting for signals and thus stored on the raised pedestrian platform should be minimized. Curbing along the cycle track should disappear at the raised pedestrian platform at Canal/Haverhill Sts. to avoid mishaps and to comply with ADA regulations.
8. Design lanes for movement on Causeway St. carefully. Preliminary designs indicate four 10.5’ vehicular lanes, a 5’ cycle track in each direction (possibly combined), a median strip of 6’ located between the two cycle tracks, and restrictions on existing turning movements at both Canal and Friend Streets.
WITHIN THE SITE
1. Reflect by design the number of pedestrian movements anticipated in Champions Way.
Where Champions Way meets the entrances to the TD Garden and the rail station concourse, pedestrians will be passing through between:
• The Green and Orange Line subway stations and the Commuter Rail Station
• The Commuter Rail Station and TD Boston Garden
• The Green and Orange Line subway stations and TD Boston Garden
• Canal St. and the Commuter Rail Station
• Canal St. and TD Boston Garden
We are concerned about the dimensions of this complex entrance and especially the ‘mixing bowl’ near the entrance to the TD Garden and suggest a detailed analysis to explain its ability to fully, conveniently and safely handle the many pedestrian demands to be placed on it.
2. Reconsider the dimensions of the MBTA underground passageway between the ‘mixing bowl’ and the subway station to maximize pedestrian convenience, safety and service. It has a 90-degree turn at one location, along with an inconsistent width progressing through the site. Additional width may be essential at the 90-degree turn. The queue of pedestrians at the bottom of the escalators should have adequate space for waiting.
3. Add a stairway inside the ‘mixing bowl’ to avoid overcrowding of the escalator and elevators. A stairway would also offer an opportunity for people to exercise during their on-site walk from the subway to the Garden or the commuter rail concourse.
4. Provide generous space for pedestrian circulation in and around the first floor at Champions Way.
The DEIR design has two escalators, two stairways (leading upward only) and two elevators (leading downward only.) Space is provided on both sides for people walking through between Canal Street and the rail station concourse. It is important that these facilities and spaces are matched closely to anticipated pedestrian traffic. It may also be important to look forward to future pedestrian traffic to be certain that the spaces and facilities are able to handle projected demand. For example, escalator redundancy may be a consideration to assure that pedestrian traffic moves without impediments.
BEHIND THE SITE
1. Commit to financial aid for the construction of the Charles River Southbank
pedestrian/bicycle bridge over the MBTA tracks. This proposal has been on the agenda for a considerable time. It has been proposed to complete the various pedestrian/bicycle projects along the Charles River in the vicinity of North Station. It will benefit all of the users on the South Bank of the river, and will aid non-motorized traffic to reach the site of this project.
WAYFINDING
1. Signs and other indications of routings for pedestrians should be provided to aid walkers and to direct pedestrian traffic to certain entry points.
We appreciate your consideration of our comments and look forward to your responses to them. Please feel free to contact WalkBoston with questions you may have.
Sincerely,
Robert Sloane Wendy Landman
Senior Project Manager Executive Director
Arlington Massachusetts Avenue Redesign Regional Advocate Comment Letter
Massachusetts Secretary of Transportation
From: Phil Goff, Co-Chairman, East Arlington Livable Streets Coalition
David Watson, Executive Director, MassBike
Wendy Landman, Executive Director, WalkBoston
Charlie Denison, Advocacy Committee Chair, LivableStreets Alliance
Chris Hart, Director of Transportation Projects, Institute of Human Centered Design
Pete Stidman, Executive Director, Boston Cyclists Union
Re: Arlington Mass Ave Corridor Plan redesign project
Date: March 28, 2013
Dear Secretary Davey:
As a group of neighborhood and regional advocacy organizations that promote Complete Streets, safer walking and bicycling, and sustainable transportation planning policies, we are unanimous in our support of the Town of Arlington’s current plan for the reconstruction of Massachusetts Avenue from the Cambridge line to Arlington Center. The Town’s current plan includes the reconfiguration of the de facto four-lane street into a three-lane roadway with striped bike lanes, wider sidewalks, improved crosswalks with refuge islands and an assortment of streetscape enhancements. We are collectively writing to express our concern that MassDOT may give too much weight to a non-binding ballot question on the local ballot in Arlington that contradicts state policies and guidelines.
Public support for the Mass Ave project is strong throughout East Arlington and among a number of businesses in the Capitol Square business district. This has been made clear in numerous meetings in the past three years, including MassDOT’s 2011 25% design hearing where over 60% of the public comments were made in support of the three-lane plan. More recently, MassDOT’s Feb 26th 75% hearing drew hundreds of supporters from throughout the Town and public comments in support ran 3:1 versus those opposed. The Arlington Board of Selectmen unanimously supports the plan and would like to see the four-and-a-half year process come to a conclusion soon.
Similar to other projects that promote a reduction in the available space for motor vehicles, opposition has formed among some neighbors and businesses. For the past four years, the opposition group has become more entrenched and has tried to delay or stop the project on numerous occasions. Most recently, opponents to the current three-lane plan gathered enough signatures to place a non-binding referendum on the April 6th ballot for Town elections. The question simply asks if Arlington voters desire to “retain four lanes on Mass Ave in East Arlington as currently practiced.”
The question discusses none of the safety benefits of the three-lane plan, whether four lanes would accommodate MassDOT design guidelines or the potential impact on funding of a “yes” vote. While we respect the use of a ballot referendum to guide local decision-making, the simplicity of the question is an inappropriate response to a complex roadway design and engineering project. A resulting “yes” vote to recommend a four-lane plan would contradict MassDOT guidelines for safe bicycle accommodations and puts numerous pedestrian safety features at risk. Four travel lanes would also contradict the goals set forth in the Healthy Transportation Compact, the GreenDOT policy, the Governor’s “Way Forward” and the Mode Shift Goals to triple the share of walking, bicycling and transit use by 2030.
The Board of Selectmen has made clear their support for the project and, short of an extremely-unlikely lopsided vote, will continue to support a three-lane design in accordance with state policy and guidelines. However, in both individual meetings and at the 75% hearing, Town officials and community members have received mixed messages from MassDOT staff about the potential results of the referendum. This included hints that a majority “yes” vote for four lanes could endanger state support and funding for the current three-lane plan. This possibility is a serious concern to our organizations as a worrisome precedent to future roadway reconstruction projects that incorporate pedestrian and bicycle enhancements that may be controversial.
In conclusion, we strongly encourage MassDOT to maintain support and full funding for the reconstruction of Mass Ave in Arlington no matter the results of the simplistic non-binding referendum. To abandon support would send a message that MassDOT is unwilling to stand behind its own Complete Streets policies, guidelines and goals, and would encourage opposition to Complete Streets in projects throughout the Commonwealth.
CC: Tom Broderick, Chief Engineer, MassDOT
Kim Sloan, Project Manager, MassDOT
Senator Ken Donnelly
Representative Sean Garballey
Representative Dave Rogers
Kevin Greeley, Chair of the Arlington Board of Selectmen Adam Chapdelaine, Arlington Town Manager Congressman Ed Markey
Massachusetts Avenue Reconstruction Regional Advocate Comment Letter
As a group of neighborhood and regional advocacy organizations that promote Complete Streets, safer walking and bicycling, and sustainable transportation planning policies, we are unanimous in our support of the Town of Arlington’s current plan for the reconstruction of Massachusetts Avenue from the Cambridge line to Arlington Center. The Town’s current plan includes the reconfiguration of the de facto four-lane street into a three-lane roadway with striped bike lanes, wider sidewalks, improved crosswalks with refuge islands and an assortment of streetscape enhancements. We are collectively writing to express our concern that MassDOT may give too much weight to a non-binding ballot question on the local ballot in Arlington that contradicts state policies and guidelines.
Read the letter here:
WalkBoston-Comment-RegionalAdvocatesMassAve_130328-Arlington