Tag: Boston

Comments on Plans for the Connect Historic Boston project

Comments on Plans for the Connect Historic Boston project

March 12, 2014

William R. Egan, PE
Chief Civil Engineer
Boston Department of Public Works
Boston City Hall, Room 714
Boston MA 02201

RE: Comments on the current plans for the Connect Historic Boston project

Dear Mr. Egan:

WalkBoston has reviewed the most recent plans for the four projects within the Connect Historic Boston program – Commercial Street, Union Street (and the Blackstone Block), Joy Street and Causeway Street). We offer the comments below.

Commercial Street
Of the four projects, we feel that this project does not seriously affect walkers. The Commercial Street project has been carefully designed to incorporate cycle tracks into the existing street layout without affecting pedestrian access or sidewalk availability. We note that the current design provides visual and physical separation between bicycles and pedestrians along the new cycle track/sidewalk proposed on the harbor side of Commercial Street.

Union Street/Blackstone Block
The proposed improvements on Union Street appear excessively vehicle oriented. The proposed sidewalk along the Blackstone Block side of Union Street is intended to encourage pedestrianism and sidewalk cafes, but does not appear to have enough space to accomplish both goals. Thus pedestrians will be walking in the raised street with vehicles. This suggests the need for a very low speed limit on this block (5-10 mph).

The space being devoted to parking could be incorporated into the raised and combined street/sidewalk and used only by pedestrians. Movement by vehicles would not be impeded by enlarging the area intended for pedestrians. One lane should be sufficient for the vehicles that would use this street in the future, and would serve emergency vehicles, and not general traffic. Loading for adjacent businesses might be accommodated in a time-based method, such as that used in the Downtown Crossing shared streets – Washington, Winter and Summer.

The sharing of Union Street between vehicles and pedestrians should be reflected in signage. The shared street area should be signed as a ‘Shared Street” at the entrance to the street with a speed limit of 5-10 mph. Drivers are not being deprived of movement through the area, because they have an alternative parallel street – Congress Street – which is very close. The speed limit should also reflect that this area, bounded by historic buildings and a park, is a prime tourist district, where walkers may not be aware that vehicles are likely to be alongside as they walk from the park to Union Street businesses.

Joy Street
Joy Street is also to become a shared street, with the street raised to sidewalk level. Streetsharing by vehicles and pedestrians requires appropriate signage at the entrance to this street, such as a ‘Shared Street” sign with an accompanying speed limit of 5-10 mph. This is especially important in this densely settled residential area, where Joy Street is often used as a vehicular cut-through street from Beacon Street to Cambridge Street.

Causeway Street
Raised street crossings for pedestrians at the intersections of Canal and Haverhill Streets had long been a part of the planning. We think that their removal is a serious mistake for pedestrian safety. Thus, we offer other suggestions that might be incorporated into the plan to improve safety for walkers. These include:

  •  A right turn lane at Canal and Causeway Streets
    The potential for drivers leaving Canal Street northbound and turning left onto Canal Street appears difficult to resolve. To avoid this issue, 3” bumps in the center of the Intersection of Canal and Causeway have been proposed. We feel these bumps are potential tripping hazards for the walkers who will surge across this intersection during morning and evening commuter rail commuting times and before and after major events at the TD Garden. In large groups of people, many will simply not see the bumps and may fall on encountering them.

Another way to prevent left turns is to change the street geometry. A very tight, single lane right turn lane could be provided to direct northbound traffic onto Causeway Street. A bulbout on the west side of the Canal Street intersection where it meets the sidewalk could divert all vehicles to the right, and could include a rollover curb to permit fire engines to make the left turn in emergencies.

 

  •  Level crossing on sidewalks on each of the side streets
    All of the side street pedestrian crossings along Causeway should be raised to sidewalk level at the entrance to intersections. This would help to reduce speeds and assist in warning drivers to make only safe and permitted movements. A level crossing could be combined with the right turn lane suggested for the Canal Street crossing.

 

  • Canal Street intersection striped from corner to corner
    The volume of pedestrians crossing the Canal Street intersection is one of the largest in the city. Surge traffic from commuters and the attendees of TD Garden events suggests that the intersection needs significant protection for pedestrians. We urge the painting of the entire intersection (curb-to-curb in both directions) to indicate that pedestrians may cross safely anywhere within the intersection. Within this ultra-wide zebra crossing, a modification could be made by painting with a different color the route of the cycle track within the intersection.

 

  • Elimination of right turn on red at all Causeway Street intersections
    It is appropriate to have vehicular traffic in all directions stopped to permit walkers to cross safely and to prohibit any kinds of turning movements that might infringe on walking movements. For example, at Canal Street, forbidding right turns during pedestrian crossing cycles would help protect walkers.

 

  • Wider crosswalk between T station entrances on Haverhill Street
    The crosswalks on Causeway Street at Haverhill Street connect directly on both ends to subway access points. This crosswalk has the potential of attracting numerous pedestrians. The crosswalks should be enlarged beyond the standard widths to accommodate surge flows. • Cobble warnings Cobbles or other rough paving should be placed on the approaches to both the Canal Street intersection and the Haverhill Street intersection to warn drivers of pedestrian concentrations ahead. The cobble warnings should be supplemented with signs indicating that pedestrian crossings are ahead.

 

  • 20 mph speed zone
    The frontage along Causeway Street is about to become even more intensely used than at present. In addition to the rail commuters and event attendees, a very large development with millions of square feet and many new residents and workers is to be placed between the Garden and the front of the property. This intensely developed area will increase the pedestrian concentration at all intersections, but principally at the Canal Street crossing. Because of the many modes of transportation and the concentration of pedestrians at this location, the speed limit should be made a cautious 20 mph on Causeway Street for the safety of all.

We appreciate your consideration of our comments and look forward to your responses to them. Please feel free to contact WalkBoston with questions you may have.

Sincerely,

Robert Sloane
Senior Project Manager

Comments on Notice of Project Change for the Mohegan Sun Massachusetts in Revere EEA #15006

Comments on Notice of Project Change for the Mohegan Sun Massachusetts in Revere EEA #15006

March 7, 2014

Secretary Richard K. Sullivan, Jr.
Executive Office of Energy and Environmental Affairs (EEA)
100 Cambridge Street, Suite 900
Boston MA 02114

RE:  Comments on Notice of Project Change for the Mohegan Sun Massachusetts in Revere EEA #15006

Dear Secretary Sullivan:

WalkBoston has reviewed the Notice of Project Change (NPC) for the Mohegan Sun Massachusetts project in Revere and offers the comments below.

The NPC was prompted by the shift of the project location to Suffolk Downs property that is located solely in Revere. This change will have significant impacts on pedestrian movement into and through the project. The elements of the project – two hotels, large gaming space, numerous restaurants and spa– have not changed. But, in the new location, the buildings have a substantially reduced footprint and are much closer to existing business and residential areas.

Walking Access to Transit – Beachmont MBTA Station

The principal impact of the project change for people arriving on foot is the much greater proximity of the development to transit access, now shifted to the Beachmont MBTA Station (formerly focused on the Suffolk Downs Station). The revised location for the proposed resort places the main entrance only 300 feet from Beachmont Station, and will likely shift some trips from autos to transit because of this proximity.

In order to encourage transit and walking trips, we suggest exploring several pedestrian amenities including the following:

  • A significantly wider sidewalk along Winthrop Avenue between Beachmont Station and the site of the resort.
  • An weather-protected sidewalk along Winthrop Avenue between the primary entrance and exit locations at Beachmont Station to Washburn Avenue. The canopy or arcade should connect directly to the existing MBTA station entrance which already has weather protection.
  • A weather-protected walkway from the edge of the resort property on Washburn Avenue to the main resort entrance.
  • Significant upgrades in wayfinding inside Beachmont Station and along the route to the resort to encourage transit ridership and reinforce the convenient transit access.
  • Upgrades of escalators and elevators inside Beachmont Station to adequately and safely handle greater numbers of riders using transit.
  • Signalization or signage protection for pedestrians crossing Washburn Street on the south side of Winthrop Avenue.

Traffic Mitigation

We are fearful that the project will add a great deal of traffic to an area that cannot handle it easily. Winthrop Avenue and the Revere Beach Parkway are heavily used already. Improvements to the interchange with Route 1 will only add to the use of these streets, which cannot easily accommodate them.

Better access might be provided via Tomesello Way, from Route 1A the Suffolk Downs Racetrack parking areas, which will have greater capacity for storage of vehicles and a more orderly approach to the casino. We think the proponent would be well advised to encourage use of Tomesello Way and the MBTA Blue Line for principal access points into the casino property.

In addition, the parking garage is enormous, suggesting a commitment only to vehicular access. Perhaps the proponent could save some of the construction cost of this garage through the use of thoughtful techniques of encouraging patrons not to drive – perhaps a benefit of some sort that patrons could use on the floor of the casino.

We appreciate your consideration of our comments and look forward to your responses to them.

Please feel free to contact WalkBoston with questions you may have.

Sincerely,

Robert Sloane
Senior Project Manager

Cc Massachusetts Gaming Commission
Mayor Dan Rizzo

Comments on the Draft Environmental Impact Report for Wynn Everett, MEPA #15060

Comments on the Draft Environmental Impact Report for Wynn Everett, MEPA #15060

February 10, 2014

Secretary Richard K. Sullivan, Jr.
Executive Office of Energy and Environmental Affairs (EEA)
Attn: Anne Canaday
100 Cambridge Street, Suite 900
Boston MA 02114

RE: Comments on the EIR for Wynn Everett, MEPA #15060

Dear Secretary Sullivan:

WalkBoston offers the following comments on the Wynn Everett Draft Environmental Impact Report. While we are pleased to see that the DEIR includes the proposal for the harbor walk and water transportation docking facilities, we are concerned about the traffic impacts and the lack of sufficient preparation for pedestrian access to the site. Improved pedestrian access is crucial to encouraging transit use as a significant travel choice for both employees and patrons.

Our comments are organized around two key issues: (1) enhancing and encouraging walking and transit, (2) mitigating the impacts of auto trips.

Enhancing and encouraging walking and transit
An Everett casino should be viewed through the lens of an urban re-development project that fits within its neighborhood and enhances the lives of its neighbors as well as its patrons and employees. In order to do that, the development should maximize the number of transit and walking trips, and minimize the number of auto trips.

1. Transit access and emphasis.
As currently planned, primary subway transit access will be provided by the Orange Line Sullivan Square MBTA Station which is about .75 miles from the site. Transit stations at Wellington and Assembly Square are each over 1.5 miles from the site, and currently have indirect, time-consuming pedestrian routes to the proposed casino. Transit should be encouraged through a number of different carrots and sticks.

• Bus service should be enhanced by improving nearby bus stops or providing subsidies to provide additional service for nearby routes. The safe use of bus stops on the far side of Route 99 is especially important to consider; the proponent should assure that there are traffic signals at all bus stops to provide safe passage for pedestrians crossing at these locations.

• Providing an off-site, transit-convenient and/or shuttle-served location for parking used by the majority of employees is one important option. The connection of proponent- or operator-controlled shuttles to these locations will reduce the impact of vehicles at the access points into the site. To attract patrons to use the bus, the proponent may want to experiment with shuttles that are attractive and “fun.”

• The proponent has included shuttle buses to nearby subway stations and to offsite parking lots. Frequency of the proposed service should allow Orange Line and bus riders to be served within very short (maximum 15-minute) wait times. All shuttle services should be made free for employees and patrons.

• The proponent and operator of the casino should price parking spaces to discourage parking during all times of day and evening during which transit service is available.

• Carpooling should be encouraged and subsidized for employees who live outside the MBTA service area or who work late-night shifts.

• The proponent should subsidize ferry services to make use of the proposed water transportation facility.

• The proponent should establish a transportation management organization that can efficiently deal with transit encouragement through subsidized transit passes, and other means that encourage the use of transit.

• Monitoring and reporting on the successes of the proponent and operator of the site in reducing vehicular traffic should be undertaken on an annual basis for the first 10 years of use of the new facilities.

2. Pedestrian access improvements
• Significant improvement of pedestrian access to Sullivan Station should be included in the proponent’s transportation mitigation plan. Access for pedestrians along Lower Broadway remains a concern. When Route 99/Broadway was reconstructed by the state, new bicycle lanes were added in both directions, but the existing sidewalks were narrowed to permit expansion for other transportation modes. The proponent should detail the ways in which sidewalks will be upgraded for pedestrian access into the site. Improved sidewalk access should extend at least as far as the MBTA Sullivan Square Station, which will require the proponent to work closely with the City of Boston.

• The new intersections serving the site should be carefully planned to include safety measures for pedestrian crossings. This should include pedestrian phase timing at these and other signalized intersections constructed or modified as part of the proposal.

• The potential new pedestrian and bicycle connection that the proponent proposes to create an approximately .75 mile direct route between the site and Santilli Circle – is intended to encourage pedestrian traffic. The proponent should be required to continue its work with the DCR and the MBTA to assure that this very short, relatively inexpensive connection actually gets constructed. The proponent should promote use of this route to encourage its use.

• A connection between the site and the City of Somerville could be provided by access over the Amelia Earhart Dam. This connection would lead to both the new Assembly Square MBTA Station and to the Somerville/Charlestown Mystic River path network. A connection across the dam could make the Assembly Square station the closest transit access point for the site. The proponent should work with the cities, as well as the DCR and the MBTA (owners of the land) to see whether this long sought pedestrian amenity that would link the extensive riverfront path networks on the two sides of the river, could be provided by the project.

• A concept plan for the streetscape in Everett has been mentioned. We trust that the plan, if developed, will be generous in its recommendations for pedestrian access.

Mitigating/managing the impacts of auto trips
We are concerned that the location of the site and its considerable distance from centers of population and regional transit stations will result in motor vehicles providing the majority of the access to the site, as the proponent has stated. The emphasis on access for vehicular traffic via Broadway leads to potentially difficult traffic concentrations – not only for Broadway, but also for Sullivan Square and the Sweetser Circle at Route 99/16. Both of these locations are already challenged by daily traffic patterns and the addition of casino traffic would seem to bring new and extensive challenges.

All of the access via Sullivan Square will deeply affect the Charlestown neighborhood and its plans for improvements at Sullivan Square. The proponent should work closely with residents of Charlestown and the City of Boston to reach an improved understanding of potential traffic volumes and impacts and the methods that might be used to partially mitigate the effects on the neighborhood. This should include traffic data collection and analysis, and detailed work with the City of Boston to review and assess all options for mitigating the impacts that casino related traffic will have on city streets, intersections and sidewalks. A community agreement between the City of Boston and the proponent should be reached prior to further planning.

Thank you for considering our comments. Please feel free to contact WalkBoston with questions you may have.

Sincerely,

Robert Sloane
Senior Project Manager

 

——————————————————————————————————————-
Join our Mailing List to keep up to date on advocacy issues.

Like our work? Support WalkBoston – Donate Now!
Connect with us on Twitter and Facebook

Government Center Garage Redevelopment Environmental Notification Form EOEA #15134

Government Center Garage Redevelopment Environmental Notification Form EOEA #15134

February 7, 2014

Secretary Richard K. Sullivan, Jr.
Executive Office of Energy and Environmental Affairs (EEA)
100 Cambridge Street, Suite 900
Boston MA 02114

RE: Comments on the Government Center Garage Redevelopment Environmental Notification Form (ENF)

EOEA #15134

Dear Secretary Sullivan,

WalkBoston appreciates the opportunity to provide comments on the Environmental Notification Form (ENF) for the Government Center Garage Redevelopment.

The proposal calls for partial demolition of the underutilized Government Center Garage as an early action, with subsequent demolition and redevelopment to take place over a number of years. Initial demolition will result in opening Congress Street to daylight and allowing redevelopment of the East Parcel, including a new public plaza and pedestrian connection between the Bullfinch Triangle and Greenway. The east parcel is a critical pedestrian link between Downtown Boston and North Station/Bulfinch Triangle, as well as a link to the Rose Kennedy Greenway. The total development will include 812 new housing units, 196 new hotel rooms, over one million gross square feet of office, and 82,500 gross square feet of retail. The garage will continue to provide sufficient parking for the new onsite uses, commercial parking for transient users as well as overnight resident parking.

We offer the following comments:

1. We believe the proposed development will improve the area for pedestrians compared to existing conditions. The existing garage is a large, foreboding structure from the pedestrian viewpoint. While the potential removal of the garage and the reopening of Congress Street to the sky is appealing in its own right, the proposed development offers additional benefits. As the project is refined during subsequent reviews, MEPA and the BRA must ensure that these benefits are not lost during revisions or project changes. We trust that any project approval will condition the following proposed improvements to ensure they are included in the final design:

  • The removal of overhead parking decks and associated office space, returning sunlight to Congress Street.
  • The proposed pedestrian-only extension of Canal Street through the newly-configured east parcel that greatly benefits heavy rush-hour foot traffic to/ from North Station.
  • The narrowing and redesign of Sudbury Street, including elimination and replacement of angled Police Department parking from the right-of-way.
  • The extension of Bowker Street to make it a through street, eliminating the stairs between Sudbury Street and the existing dead end of Bowker Street.
  • The project could potentially provide very substantial benefits that would have a lasting effect on the built environment of the immediate neighborhood and the entire downtown core of Boston. Careful attention must be paid to the pedestrian experience in and around the site to take advantage of its tremendous pedestrian and transit access. The project is positioned to capitalize on these features and it is incumbent upon MEPA, the BRA and the City of Boston to ensure that the final design fully accounts for these opportunities.

2. Curb cuts for the garage – All curb cuts provided for the new garage should be kept to a minimum width, should enter the street at a right angle, and should be at sidewalk grade (no curb cut for pedestrians). Appropriate vehicle exiting warning signs must be provided for pedestrian safety. The existing garage access drives are too wide and pedestrians on the sidewalk are often threatened by automobiles traveling at high speeds into and out of the garage’s overly wide parking access ramps.

3. MBTA on-site improvements – The project should not interfere with normal MBTA bus operations, and allowance must be made for continued bus and subway service connections on-site. The proponent and the MBTA should commit to additional design work to improve the walking environment in this area to accommodate the large number of pedestrians using transit, along with the additional pedestrian volumes that will be generated by this very large project.

4. Hawkins and Bowker Streets – Bowker Street should become a through street with a changed gradient that allows an ADA compliant sidewalk. If Hawkins Street cannot also be made a through street, the stairs that connect its dead-end at Sudbury Street should be re-graded into an ADA compliant sidewalk.

5. North End Access – While the project claims to reconnect long divided Boston neighborhoods, it fails to offer the North End the same pedestrian benefits it does for the West End, Government Center and Bullfinch Triangle. In fact the project design seems to turn its back on the North End. A North End pedestrian connection should be explored in greater detail. The connection should work to interconnect the north-south walkway through the east parcel, North End residents, the two Green and Orange Line MBTA subway stations, and the Greenway.

6. Walk Signals – The existing pedestrian walk signals at the intersection of New Chardon Street and Canal Street will need to be adjusted. The pedestrian service from Canal Street through the newly configured east parcel will siphon existing North Station foot traffic away from adjacent streets. As a result, this pedestrian walk signal and the narrow mid-crossing island may be overwhelmed by the additional foot traffic on Canal Street. All walk signals on New Chardon, Friend, Sudbury and Merrimac Streets should be adjusted to handle the additional pedestrian traffic that the project will create.

7. Narrowing Sudbury and New Chardon Streets – A detailed study of the potential for narrowing both Sudbury and New Chardon Streets is essential. Such a study should include provisions for wider sidewalks, coordinate with improvements being planned for neighboring streets as part of the Crossroads Initiative and potential bike lanes. Further pedestrian crossing improvements should be explored including the elimination (or infill) of the truck turning lanes at the corner of Merrimac Street and New Chardon Street, and at the corner of New Chardon Street and Congress Street.

8. Other pedestrian ways – The document does not address whether the proponent will maintain or improve pedestrian connections that skirt the northwestern edge of the site, from New Chardon Street, up the Brattle Way pedestrian mall and ultimately out towards Cambridge Street. This pedestrian mall/walkway and associated small park area is well used during the day and it should be considered with the project’s design. The short length of Brattle Way could be an excellent candidate for expanded pedestrian use.

Thank you for the opportunity to comment on the ENF for the Government Center Garage Redevelopment. We believe this site provides an opportunity to develop a transit-oriented, mixed-use project that could showcase pedestrian friendly sidewalks and streets. We hope our comments on the ENF/PNF are incorporated into your requirements for the next phase of design and permitting documents.

Please contact us for any clarification or additional comments that would be useful.

Sincerely,

Wendy Landman                                    Robert Sloane
Executive Director                                  Senior Planner

Comments on Charles River Basin Connectivity Study

Comments on Charles River Basin Connectivity Study

December 16, 2013

Richard K. Sullivan, Jr.
Executive Office of Energy and Environmental Affairs
Attn: Dan Driscoll
100 Cambridge St., Suite 900
Boston MA 02114

RE: Comments on the Charles River Basin Connectivity Study

Dear Secretary Sullivan:

WalkBoston has reviewed the Charles River Basin Pedestrian and Bicycle Study for Pathways and Bridges, the so-called Connectivity Study. Our comments arise from the document and from the recent presentation of the study to the public.

The Connectivity Study is very exciting work, as it assembles the issues of movement along the basin very effectively, and points out the possibilities for positive changes in the paths, walkways and running facilities along the River. DCR should be very proud of this feat, and should proceed into implementation of priority aspects of the planning effort as soon as possible.

We were particularly heartened by the Study’s general recommendations for the Basin: “DCR should strive to develop a 10’-wide paved path with a parallel soft-surface trail or shoulder for runners (emphasis added) where possible….. In “pinch point” conditions, a minimum 8’ paved path, with 3’ shoulder on one side, should be incorporated.”

This acceptance of separate paths for runners and joggers – and also pedestrians – is a very important aspect of the planning and represents continuity with past planning efforts.

In the 2002 Master Plan for the Basin a stated goal was to provide safe and continuous bicycle, skating, and pedestrian access along the entire length of the Basin, with a “separation of footpaths and bike paths where doing so will not create excessive pavement near the shoreline.” The master plan also called for reducing congestion and minimizing conflicts on the paths (presumably conflicts between bicycles and pedestrians).

In 2005, users were surveyed to discern attitudes about the river facilities. The survey asked respondents to list and rank how they used the Basin. The top twelve responses were, in order of frequency:
Walking for pleasure
Attending concerts or events
Relaxing in the park
Driving on the parkways
Running or walking for exercise
Biking
Using Riverbend Park in summer
Picnicking
Enjoying the outdoors with children
Inline skating
Walkathons
Informal sports

More than sixty percent of those surveyed used the Basin more than once a week for strolling, relaxing, attending concerts or attending special events. Eighty-six percent asked for easier and safer pedestrian access to the Basin, and an equal proportion recommended separating pathways by user types. Users also frequently called for more benches and places to sit, more wildlife areas, more park rangers, and more convenient parking.

If the Continuity Study can be regarded as an update to the Master Plan, we think it may be leaving out some of the emphasis that the authors of the two planning documents clearly stated. In particular, the separation of bicycle and pedestrian paths does not seem to be as important an aspect of the plan as the users of the park suggested to be of high importance. WalkBoston believes that path separation should be integral to all elements of the plan, as it will help deal with the many problems inherent in an area that is so heavily used with so many potential conflicts between users.

We urge consideration of the following:
1. The elimination of conflicts between users of the paths should be uppermost as a safety precaution. Conflicts arise where bicycle traffic is moving rapidly through areas where pedestrians are strolling, causing dangerous situations for all. The conflicts are particularly difficult for commuting cyclists, some of whom are loath to slow down.

2. An expansion of the definition of ‘multi-use path’ would open options that are not clearly included at the moment. Multi-use pathways in the Basin should have an element – probably a parallel, separate path – that would cater to slow-moving walkers, runners and joggers. The foot traffic path could be built entirely separated from the paved path or built as a non-cambered shoulder.

3. Multi-use paths are appropriate for areas where there is low density of use by walkers, runners and cyclists, but should not dominate planning for the heart of the very heavily used park system in the center of Boston. Instead, the overriding goal should be provision of facilities in which space is plentiful for all park users and potential conflicts between users are minimized using methods that are appropriate to each location.

4. Existing multi-use paths should be expanded all along the river to meet the definition of separation between paths based on user needs.

5. Recognition of what runners and joggers show about their desires for facilities would help in planning new paths. Narrow dirt paths that exist informally alongside many of the paved paths in the Basin demonstrate a clear desire for a softer surface preferred by runners. The softer surfaces can also be used by pedestrians and will clearly help separate cyclists from people on foot.

6. A demonstration of the path separation is included in the proposal for the Greenough Boulevard narrowing. The effects on users would be an important element to explore.

7. Path separation in the near term may only be possible on one side of the river. The Greenough Boulevard proposal and the Memorial Drive narrowing between the Eliot and Anderson Bridges point in the direction of path separation as a major feature on the north bank. Continuation of path separation both west and east of these two segments would be a next logical step. Except at intersections, parkland seems to be available for new or modified paths.

8. An unfortunate aspect of all path planning along the river is the intersections with streets at the bridges. The narrow paths that exist at many of the bridges will be a major feature of riverfront paths for a long time, but should not preclude path separation away from the bridge intersections.

9. As long-term improvements, underpasses at bridge intersections are appropriate and important options that will enhance the recreational and transportation options for many Basin users.

We appreciate your consideration of our comments and look forward to your responses to them. Please feel free to contact WalkBoston with questions you may have.

Sincerely,

Wendy Landman                                    Bob Sloane
Executive Director                                  Senior Project Manager

Cc Nicole Freedman, Boston Bikes
Cara Seiderman, City of Cambridge
Steve McLaughlin, MassDOT
Margo Levine Newman, The Esplanade Association
Renata von Tscharner, Charles River Conservancy
Herb Nolan, Solomon Fund
Jackie Douglas, LivableStreets Alliance
Pete Stidman, Boston Cyclists Union
David Watson, MassBike
Tom Grilk, Boston Athletic Association