Tag: Complete streets design

Comments on the Design for Commonwealth Avenue Phase 2A

Comments on the Design for Commonwealth Avenue Phase 2A

2 July 2014

Commissioner Jim Gillooly
Boston Department of Transportation
1 City Hall Square, Room 721
Boston, MA 02201-2026

Vice President Robert Donahue
Boston University Government & Community Affairs
121 Bay State Road
Boston, Massachusetts 02215

Re: Design for Commonwealth Avenue Phase 2A

Dear Commissioner Gillooly and Vice President Donahue:

We appreciate you taking the time to meet on Wednesday, June 25 to review the plans and process for Commonwealth Avenue Phase 2A. The redesign is an exciting opportunity to build a model street that will help achieve our collective goals for safety, enhanced user experience, and multi-modal transportation. These goals are in line with mode-shift, climate change, and public health goals set forward in Boston’s Complete Streets Guidelines, Bike Network Plan, and Climate Plan, MassDOT’s goals to triple biking, walking and transit mode share, and the goals set out in the Boston University Master Plan. The project provides a key opportunity to re-build Commonwealth Avenue to protect the needs of the area’s growing population of people who bike and walk, and address the decline of car traffic on the street and in the city.1

Unfortunately, the current designs for the project do not achieve these admirable project goals. Widening street lanes and adding fences encourages cars to move faster, making the street less safe and less comfortable for people. The plan to narrow the already overcrowded sidewalks does not serve the thousands of people who walk on Commonwealth Avenue every day. The current bike lane, which has been the site of many injuries and at least one fatality, is not significantly improved in the design, though there is a clear opportunity here to prevent more tragedies from occurring.

The safety of our community and the student population of Boston University and many other institutions in the area demands that the plans for Commonwealth Avenue Phase 2A be redesigned to protect people and meet the project objectives.

  • Increase the comfort and safety of pedestrians
    o  Minimize sidewalk narrowing to maintain adequate width for pedestrian volumes and allow businesses to maintain outdoor café seating
    o  Make crosswalks and curb ramps as wide as sidewalk walking zones
    o  Minimize tripping hazards from curb ramps, for example at the corner of Pleasant and Commonwealth Ave.
    o  Add curb extensions at all intersections
    o  Time the walk signals to allow for a single-stage crossing of Commonwealth Ave
    o  Make all walk signals automatic
    o  Add a mid-block crosswalk at Alcorn St/Naples Rd
  • Protect people biking and encourage more people to bike
    o  Explore all options to add cycle tracks (protected bike lanes) without narrowing sidewalks
    —   Parking-protected one-way cycle tracks
    —  Center-lane one-way cycle tracks (similar to those used on Commonwealth Ave in the Back Bay)
    o  Add bike boxes at intersections (traditional and two-stage turn queue boxes for those waiting to turn left)
    o Incorporate bike signals and leading bicycle phasing at intersections
  • Keep transit moving
    o  Add transit signal priority for Green Line trains and buses
    o  Add curb extensions at bus stops
  • Design for safe and steady traffic speeds
    o  Green Wave: coordinate traffic signals to bike speed (15 MPH)
    o  Make all travel lanes no wider than 10.5’ (MassDOT regularly approves this)

We understand that project funding depends on final designs by FY15. However, funding a design that does not meet the objectives of the City, the University, or Boston citizens is not a win for anyone and public controversy slows the process more than would design changes.

These designs have not had a true public process; LivableStreets Alliance, MassBike, and many other advocates and citizens submitted comments at the 25% design meetings, but heard no response and received no follow up information on the project. To redesign such an important and heavily-used street without an inclusive process is contrary to the City’s guidelines and goals.

We urge the City to engage in an inclusive public process to move plans from 25% to 100% design in order to build a street that we can all support. Past projects (including Connect Historic Boston) illustrate that the City can develop 0 to 100% design plans in less than a year.

We ask you to please respond to this letter by Wednesday, July 9, 2014 to let us know how you intend to address these concerns.

Sincerely,

Jamie Maier
Campaign Coordinator, LivableStreets Alliance

Pete Stidman
Executive Director, Boston Cyclists Union

David Watson
Executive Director, MassBike

Wendy Landman
Executive Director, WalkBoston

 

CC:
Nicole Freedman, Boston Bikes
Mike Wasielewski, BETA
Merrick Turner, BETA
Bill Conroy, Boston Transportation Department
Michelle Consalvo, Boston University
Ken Ryan, Boston University
Bill Egan, Boston Public Works Department

Attachments:

  • Comment Letter on Design for Commonwealth Avenue Phase2A
  • Marked up plans for Commonwealth Avenue Phase2A
  • Photo example of curb ramp/crosswalk as wide as sidewalk to meet high volumes
  • Photo example of cycle track
  • Bike Network Plan

Other Materials


Footnotes

 

Bike use has increased as much as 135% since 2007, pedestrian volumes have increased 80% since 2001, and car volumes have decreased as much as 31% since 1987 in the project area, according to the Boston University Master Plan (sections 8.5.1-8.5.6)

Comments on the MGM Springfield DEIR

Comments on the MGM Springfield DEIR

January 31, 2014

Secretary Richard K. Sullivan, Jr.
Executive Office of Energy and Environmental Affairs (EEA)
100 Cambridge Street, Suite 900
Boston MA 02114

RE: Comments on the MGM Springfield Draft Environmental Impact Report
EEA #15033

Dear Secretary Sullivan:

WalkBoston has reviewed the Draft Environmental Impact Report for the MGM Springfield proposal and offers the comments below.

Within the DEIR, there are some changes in the dimensions of the plan. The proposal now includes a somewhat smaller, 501,108 square feet casino resort that includes retail/restaurant uses and banquet facilities in addition to gaming space. Adjacent to the casino will be a somewhat smaller 250­‐room hotel, 54 residential units, and an expanded, 159,397 SF retail and entertainment center to be known as Armory Square. A somewhat smaller, 3,740 space on-­site multi-­level parking garage will be provided. In most cases, these alterations to the plan do not appear to affect volumes or paths for walkers.

The ENF Certificate provided by Secretary Sullivan called out additional analysis to be included in the DEIR, and specified that the proponent was to meet with WalkBoston about our comments on the ENF. The Secretary’s Certificate included this language:

“I strongly encourage the proponent to consult with WalkBoston during the preparation of the DEIR to identify opportunities to enhance the development of pedestrian access to and within the site as well as incorporation of safe pedestrian access for off-­site roadway improvements.”

The proponent did meet with us to discuss the project, and were very forthcoming about the pedestrian components of the project. In our discussion we covered many of the ideas that now appear in the DEIR and have solidified the commitment to serving walkers in the project plans and designs.

Secretary Sullivan’s Certificate on the ENF mentioned some specific aspects to be explored further in the DEIR. These are important and form the basis of our comments on the DEIR:
1. Existing and proposed traffic signals.
2. Consistency with a Complete Streets design approach.
3. Existing and proposed connections for pedestrians.
4. A commitment to making improvements to increase the use of walking routes.

1. Existing and proposed traffic signals.
We are pleased to note that the DEIR calls for updating pedestrian signal equipment at the study area intersections around the site.

We note that two mid-­‐block crossings with refuge islands and flasher assemblies are proposed – one on State Street and the other on Union Street ‐ both roughly half way between Main Street and East Columbus Avenue and located at the exterior of the proponent’s site.

Another mid-­block crossing is noted in the DEIR that allows for a mid-­block crossing to reach a bus stop. This crossing is located on Main Street at Howard Street, and represents a response to one of WalkBoston’s recurring concerns ‐ that transit riders should not be required to walk to corner locations to reach a bus stop if the stop is mid-­block. Instead, crosswalks should be added to provide safe and convenient walking routes for transit users.

We encourage the efforts of the proponent to provide a diagonal pedestrian crossing at the intersection of Main and State Streets, where a direct connection to the Mass Mutual Convention Center may be of significant use. We hope that the City of Springfield will work with the proponent to establish this crossing.

The proponent vows to upgrade pedestrian push buttons to MUTCD standards at all locations where new signals will be installed as part of this project or the mitigation efforts that result from the construction of the project. Upgrades of pedestrian push buttons are very welcome as are any other forms of enhancements for pedestrians crossing streets on the perimeter of the project.

2. Consistency with a Complete Streets design approach.
The proponent has been mindful of the design of streets on the perimeter of the project. In particular, the width of sidewalks has been discussed and the design now provides positive benefits to walkers.

For example, sidewalks on Main Street, according to several of the maps, vary in width from 10.5’ to 18.’ On the widest sidewalks, there is the promise of added pedestrian amenities, such as benches, pedestrian level lighting landscaping and other streetscape improvements. The designs of the narrowest sidewalks should be carefully considered to provide a clear walk zone of at least 5 feet, with no obstructions, such as trees or benches, intruding on that width.

We note that the pedestrian network evaluation preceding design has led to proposed improvements to sidewalk pavement conditions, sidewalk widths, crosswalks, and compliance with current accessibility standards.

One of the requirements of a complete streets approach to street design is adequate provision for buses, bus stops and transit riders. In central Springfield, including Main Street along the east boundary of the site, heavy bus traffic (including four major PVTA bus routes) serves downtown employers and merchants and ordinarily occupies a lane that can be shared with bicycles, but should otherwise be retained for exclusive use by buses.

In addition to the PVTA bus routes, a proposed downtown trolley line will connect the casino site to rail and bus service in the vicinity of Union Station, about ½ mile north of this site. The trolley line makes the connection efficiently, and will encourage transit use by casino employees and patrons.

3. Existing and proposed connections for pedestrians.
The proposal includes several connections for pedestrians into the large complex, particularly along Main Street. The proponent has made progress is the design of the proposed Armory Plaza at the south edge of the casino building by providing a car-­free area that combines the open space surrounding the old, restored Armory building with the relatively small but useful open space of DaVinci Park. The use of the Plaza may be combined with the uses in the adjacent Armory Marketplace building and may host civic events and a farmers’ market.

A new pedestrian attraction is the provision of a landscaped plaza atop the casino building. This plaza is completely removed from vehicular traffic and provides a quiet space where people may walk or sit.

A pedestrian connection already exists between the site and the Connecticut River pedestrian and bicycle trail. An existing at-grade crossing at the foot of State Street allows pedestrians to move between the proponent’s site and the trail. It is anticipated that this connection will be used as a way to get from the site to the nearest open space. Lighting under I-­91 at State Street will help open the area to pedestrians by making it more legible and safe.

A similar pedestrian connection exists at Union Street, where the walkway link that passes under I-­91 allow pedestrians to reach the Naismith Basketball Hall of Fame. The distance is relatively short and is eminently walkable. The connection will be improved by the proposed lighting to be placed under I-­91.

4. A commitment to making improvements to increase the use of walking routes.
The proponent’s site is central to the Springfield urban area and will become an integral part of downtown as it is developed. Within the site, there are many places to walk that may require little effort to get patrons to explore. Each entrance/exit to the site should have wayfinding signs to assist walkers and encourage them to walk to destinations within and outside the entertainment complex. The signs should indicate where to find locations such as the center of the casino, the hotel, the outdoor plaza, shops and theatres on the south side of the site, Former Armory, Armory Square Marketplace, the rooftop landscaped plaza, and the main entrances to the parking garage.

Outside the casino complex, there are many attractions in downtown Springfield, and wayfinding signs that guide walkers should include: the Mass Mutual Convention Center, Union Station/Main Bus Depot, Dr. Seuss Sculpture Garden, Springfield Museums, the Civic Center, Springfield Armory, and nearby parks.

Signs should also indicate how to find the riverside attractions including views of the river and the Connecticut River Pedestrian and Bicycle Trail and the Naismith Basketball Hall of Fame.

Wayfinding signs should include walking times to reach destinations. Pedestrians do not think in terms of miles, and minutes required to take a walk are much more effective in conveying the effort that might be involved. Walkers may think little of having to walk ten minutes, but recoil at the prospect of walking ½ mile, even though the distances are the same.

Specific wayfinding signs that should include walking information as well as vehicle and bicycle information are:
• Signs along West Columbus Avenue on the river-­facing side of the site,
• Signs on Union Street at the edge of the project, and
• Signs along the East Columbus Avenue side of the site.

Wayfinding can be enhanced with local walking maps that help people find their way around the site and its environs.

We appreciate your consideration of our comments and look forward to your responses to them. Please feel free to contact WalkBoston with questions you may have.

Sincerely,

Robert Sloane
Senior Project Manager