WalkBoston, LivableStreets Alliance, Boston Cyclists Union Hook Wharf Project/15-17 Northern Avenue Comment Letter

WalkBoston, LivableStreets Alliance, Boston Cyclists Union Hook Wharf Project/15-17 Northern Avenue Comment Letter

February 12, 2021

Ebony DaRosa
Boston Planning and Development Agency
One City Hall Square
Boston, MA 02201

Via Email:  Ebony.DaRosa@Boston.gov

Re: Hook Wharf Project/15-17 Northern Avenue

Dear Ms. DaRosa:

WalkBoston, LivableStreets Alliance and the Boston Cyclists Union write with our comments regarding the redevelopment of the Hook Lobster site.

Project Concept

We see a number of things to like about the project including its addition to the Harbor Walk, its support of Hook Lobster with both indoor and outdoor space, its addition of new dining venues, the incorporation of separated bike lanes along Atlantic Avenue and the provision of no on site parking spaces. We believe that the mix of Harbor Walk, Seafood store and restaurants, and hotel are appropriate for this very public site.

Construction

We are also pleased that the developer will ensure that full Atlantic Avenue sidewalk access with overhead protection will be provided throughout the construction period. We also hope that the proponent will be able to use barges to move materials onto and off the site as was described during the January public meeting. We look forward to seeing more details about construction methods during subsequent filings with the BPDA and MEPA.

We do have several concerns which we ask that the proponent address in future filings, several of these concerns will require extensive coordination with City and State agencies.

Delivery and drop-off access to the site

Given the density of public facing uses on the site, including retail, restaurant, hotel and event space a significant number of vehicle trips will need to be accommodated on the site. As described in the PNF, these operations will take place both inside the loading dock within the building footprint, and alongside the hotel, both within the site and along the site in City-owned land in and adjacent to the Northern Avenue Bridge (NAB) right-of-way, including trucks and vehicles exiting the property via the NAB approach to Atlantic Ave.

We request that the proponent’s next filing include detailed information including:

  • The number of service deliveries and drop offs onto and off the site and into the building’s loading bays
  • The number of guest drop offs and pickups to/from the site per day
  • A diagram of the paths of vehicle movements on and off the site
  • Commit to providing personnel to manage the movements of vehicles

Alignment with the Northern Avenue Bridge

While the proponent has suggested a new layout for the Northern Avenue Bridge (NAB) approach area which straightens out the City’s proposed design and makes such use more feasible from a geometric perspective, we do not believe that the mix of shuttle buses, pedestrians, bikes, delivery trucks, cabs and TNCs that are now being proposed for this area will be safe or comfortable for people walking and biking.

We are also concerned that the elevation and alignment of the NAB is not properly reflected in this plan. To date the City has not provided a detailed design for how the approach of the bridge will connect to Atlantic Ave.

We would prefer that the proponent join with the overwhelming support from community members and our walking, biking and transit advocacy organizations to urge the City to reverse its decision to allow vehicles (other than emergency vehicles) on the NAB, and rather to develop a walking and biking bridge that could much more readily allow reasonable service access for the Hook Wharf Project and the Coast Guard Building which will also need to use the NAB approach for its service vehicles.

As people walking and biking will be the primary users of the NAB, and the users that the public has urged the City of Boston to make the focus of the NAB design, if an acceptable design is possible we believe that the proponent will need to develop an improved design for the NAB approach and the hotel service area. A detailed management plan, including dedicated staffing, will be needed to ensure the safety of people walking and biking onto and off the NAB and along Atlantic Avenue.

Future North-South Rail Link

The Hook site is where the tunnel would leave the Central Artery right-of-way to access South Station. Thus a Hook Wharf building piling at the wrong location could sever this route and prevent the Rail Link from ever being built. Since a final alignment for the N-S Rail Link has not been determined, the right-of-way must be preserved. And we urge the BPDA decision on Hook Wharf to explicitly require a design that allows for the future feasibility of a N-S Rail Link via the Central Artery alignment.

Thank you for the opportunity to comment on the project and we look forward to the next round of information and public meetings.

Stacey Beuttell, Executive Director, WalkBoston

Wendy Landman, Senior Policy Advisor, WalkBoston

Stacy Thompson, Executive Director, LivableStreets Alliance

Becca Wolfson, Executive Director, Boston Cyclists Union

 

Cc:
Jonathan Greeley, Boston Planning and Development Agency
Elizabeth Stifel, Boston Civic Design Commission
Andrea Leers, Boston Civic Design Commission
John Moriarty III, Moriarty Partners
David Manfredi, Elkus Manfredi Architects
William Zielinski, SKW Partners
Carol Chirico, GSA
Kim Janey, Boston City Council
Annissa Essaibi George, Boston City Council
Michael Flaherty, Boston City Council
Julia Mejia, Boston City Council Michelle Wu, Boston City Council
Ed Flynn, Boston City Council
Greg Galer, Boston Preservation Alliance
Sara McCammond, Fort Point Neighborhood Association

WalkBoston Comments on Harbor Garage Redevelopment

WalkBoston Comments on Harbor Garage Redevelopment

October 9, 2020

Director Brian Golden
Boston Planning and Development Agency
Attn via email: Ebony DaRosa

Secretary Kathleen A. Theoharides
Executive Office of Energy and Environmental Affairs
Attn via email: Alexander Strysky

Re: The Pinnacle at Central Wharf (Harbor Garage Redevelopment)

Dear Secretary Theoharides and Director Golden:

WalkBoston is Massachusetts’ leading pedestrian advocate. We frequently provide comments on major public and private development and infrastructure projects, with a focus on how those projects serve and affect people walking, biking and taking transit.

The redevelopment of the Harbor Garage has been under discussion for many, many years with major public disagreement about the appropriate scale and mix of uses that the project should comprise. We will not specifically weigh in on those issues because the Municipal Harbor Plan has now set the stage to allow a very large mixed-use development. And while a number of commenters will raise public process issues, broad public benefit issues and questions about the timing of required design and use standards as they apply to the timing and design of this project we look to others to provide detailed and focused attention on these issues.

Our comments focus on a more detailed and fine-grained set of concerns about the ways in which people walking, biking and taking transit to, through and next to the project will be affected.

From a site planning perspective, we believe that the current proposal has a better footprint and urban design than earlier development concepts. Improvements to the sidewalks, landscaping and scale of the pedestrian areas around the site will  contribute to a more comfortable and attractive streetscape than the existing conditions surrounding the garage. However we do have significant concerns.

Garage and loading access

Our significant and consequential comment is that garage access and egress should be removed from Atlantic Avenue in order to provide an acceptable site plan that will be safe for people walking and biking along Atlantic Avenue. 

The building site presents a complicated puzzle for the circulation of people and vehicles because all four sides of the site are public facing, each with its own personality and constituency.

Atlantic Avenue

  • Over many years, the advocacy community has invested an enormous amount of time and energy to establish and preserve the integrity of a wide and pedestrian-friendly sidewalk along Atlantic Avenue, both as a core walking route for thousands of people every day and as a component of the Rose Kennedy Greenway. We remain committed to maintaining the preeminence of this walking route. Atlantic Avenue’s significant pedestrian volumes can only be expected to grow in the coming years.

Milk Street

  • Milk Street is the primary connection from Downtown and the Greenway to the Aquarium,  serves millions of visitors every year, and will be part of the Aquarium’s planned Blueway. Special attention to this walking link to the harbor is an essential component of the site’s redevelopment.

Harbor Walk

  • The Harbor Walk is the City’s waterfront front door and pedestrian corridor with critical public realm and resiliency functions and serving thousands of walkers every day. As one of Boston’s most loved and important pedestrian assets and spaces, the Harbor Walk deserves great attention to design, programming and management.

East India Row

  • East India Row provides access to both the project site and the Harbor Towers residential development. It is used by both pedestrians and vehicles as a key link between Atlantic Avenue and these sites.

Vehicle Access

As currently configured and programmed, vehicle access into the garage for most of the garage users and all of the building deliveries will require vehicles to cross the Atlantic Avenue sidewalk. Access via this garage entrance will be for all passenger vehicles for office, retail, Aquarium and public parking, and for all loading (residential, office, retail). Egress across the sidewalk will serve all loading (residential, office, retail). As shown on the plans in the PNF, the driveway serving the garage entryway looks almost as wide as Milk Street.

According to the PNF (Table 2-7), during the morning peak hour there will be 292 vehicle trips turning across the Atlantic Avenue sidewalk – or about 5 vehicles/minute. The pedestrian data provided in Figure 2-7B indicates that under existing conditions approximately 700 pedestrians walk along Atlantic Avenue during the morning peak hour – or about 12 people/minute. The volume of vehicles turning across this busy sidewalk, without traffic signals to provide a safe time for pedestrians to walk along the sidewalk, is comparable to the right turn volumes of 238 vehicles from Seaport Boulevard onto Atlantic Avenue during the weekday PM peak hour (see Figure 2-6B), and the pedestrian volume walking along Atlantic Avenue of 738 people is also comparable. (PM pedestrian trips along Atlantic Avenue at the project site are even higher than AM trips, so a shift from garage access to garage egress would create even greater conflict.)

Bike volumes in the Atlantic Avenue bike lane are approximately 60-80 bikes/peak hour under existing conditions.

The PNF does not include projected walking and biking volumes (it does include those projections for vehicle trips). Given the rising numbers of walking and biking trips that we are seeing across downtown Boston, we request that these projections be included in the Draft EIR and PIR.

No specific information is provided about the number of loading trips that will enter and leave the building across the sidewalk. This information should also be provided in the Draft EIR and PIR.

In addition to the safety hazards of vehicles turning across people walking and biking, we also believe that vehicles exiting (and possibly entering) the garage will queue up across the sidewalk as they wait to enter the travel lanes along Atlantic Avenue (or potentially as they wait to enter the garage itself).

We do not believe that a garage and/or loading entrance into the project site should be allowed on Atlantic Avenue because it would require vehicles to turn across the sidewalk and bicycles traveling along Atlantic Avenue. We ask the City to require a shift of garage access to East India Row where it will impact far fewer people walking and biking, and where it will not negatively impact one of Boston’s premier walking routes. 

Aquarium and Harbor Towers Parking Long-Term and During the Construction Period

Because the site will continue to provide parking for the Aquarium (as required under the Municipal Harbor Plan) and also for the Harbor Towers, as well as serving the Project’s commercial, retail and residential occupants, it is not realistic to ask that the garage use on the site be eliminated. However, we urge the Proponent, the City, the Aquarium and Harbor Towers to re-examine the amount of parking included and reduce it to the greatest extent possible.  Additionally, we urge the developer to explore the feasibility of repurposing any reduction  of parking into maximizing the number of onsite affordable housing  units.. As the City is in the midst of revising its maximum allowable parking regulations, this Project should at a minimum adhere to these new lower limits. Any reduction in total vehicle trips into the site will reduce the Project impacts on people walking and biking as well as its contributions to traffic and greenhouse gas emissions.

We understand that publicly available parking spaces are needed for the Aquarium to maintain its operations – and especially in light of the financial hardship caused by the ongoing COVID-19 pandemic, it is critical to insure the Aquarium’s healthy operations when the Harbor Garage is out of service. Given that the City and the Proponent will be working closely with the Aquarium to develop a parking plan for the approximately 3-year construction period when there will be no parking at the site,  we believe it would be valuable to explore if any of the short-term parking mitigation sites may serve as a better long-term parking solution than building 500 new parking spaces.

Site Design, Operations and Management Comments

  • Pedestrian circulation around and through the development site
  • Site grade in relation to the surrounding waterfront
  • Public programming to support a lively public realm and welcome a diverse set of visitors
  • Shadow, wind and microclimate
  • Coordination with existing and future waterfront resiliency efforts that will affect people walking

Pedestrian circulation around and through the development site

Pedestrian circulation around the building, on the site and through the building seems to provide attractive pedestrian routes and easy access to all the public spaces within the development. The Proponent has noted that a variety of sidewalk, accessibility and landscape improvements will be made to enhance the walking environment.

We could not find a description of whether the diagonal interior pedestrian passage through the building would be open to the public 24/7.  We ask that the Proponent describe the operating plans for this pedestrian circulation in the next filing.

Relationship between the raised grade of the proposed site plan and the surrounding waterfront

The document provides a description of the proposed grade changes to raise the site level above projected water levels in future years, but it is not clear to the lay reader how the transition between this site and adjacent sites will affect the experience of people walking on this site or adjacent sites. Please include a detailed description and diagrams in the next project filing.

Public programming to support a lively public realm and welcome a diverse set of visitors

While the document provides several sentences describing the Proponent’s intent to provide site programming worthy of this important site and significant development, very little detail is included. We ask that the following questions be addressed in the next filing.

  • How will the Proponent ensure that people of all races, ethnicities and income groups feel welcome and included in both the interior and exterior spaces of the project?
  • What low and no-cost activities will be provided?
  • What will be the annual budget for programming of public activities on the site and how many years of programming will the Proponent provide?
  • Will there be children’s programming to align with Aquarium? Will the Aquarium have the opportunity to provide (and be compensated) for such programming?
  • How will the Proponent enliven the site during winter months?

Wind, shadow, and microclimate

We are pleased that the developer has explicitly worked to design a building façade/skin that is intended to reduce the wind impacts of the building and we look forward to seeing the wind studies that will be provided in future filings.

A project of this scale will have unavoidable shadow impacts on the streets, sidewalks and open spaces around it and this project is no exception.

Given the hope that this project will invite many people to enjoy the waterfront, we urge the developer to look in detail at ways to create comfortable outdoor spaces that are sheltered from the existing windiness of the waterfront; are shaded in the summer; and take full advantage of the sun in colder months. We suggest that the design team look at best practices for creating human-friendly microclimates on the site. This could mean spray stations for the summer, seating with solid legs and backs and wind protection for the winter, and different orientations to take advantage of the sun at every season. We look forward to learning more about the designs in the next filings.

Coordination with existing and future waterfront resiliency efforts that will affect people walking

The development plan meets the City’s resiliency guidance for the development site itself. We ask that the developer formally commit to working with the City and with other waterfront property owners and managers to ensure that public access to the HarborWalk will be safe and attractive over the long term as sea levels rise.

Thank you for the opportunity to comment on this significant new project. WalkBoston would be pleased to answer any questions about our comments and to meet with City or development team staff.

Sincerely,

Stacey Beuttell
Executive Director

Walk Audit Today in Charlestown

Walk Audit Today in Charlestown

Gorgeous morning for a Charlestown walk audit with the Mystic River Watershed Association and friends. Big idea is to find new connections from the neighborhood to the waterfront and to highlight the parts of the Harbor Walk that already exist.

Comment Letter: General Electric Headquarters Project EA 15547

Comment Letter: General Electric Headquarters Project EA 15547

September 30, 2016

Matthew Beaton, Secretary
Executive Office of Energy and Environmental Affairs
Attn: MEPA Office, Alex Strysky
100 Cambridge Street, Suite 900
Boston, MA 02114

Re: General Electric Headquarters Project EA 15547

Dear Mr. Beaton,

WalkBoston has reviewed the Expanded Environmental Notification Form for this project and we
offer our comments below.

We are excited that GE is locating its headquarters in Boston, and is proposing a project that has such an urban plan where the great majority of trips to the site will be by people walking – about 70% if both walking and transit/walking trips are included. Ensuring that walking connections to the site are convenient, accessible and attractive will be critical to welcoming the public and GE staff to the headquarters.

We think there are several aspects of the site that are exciting for pedestrian access, and where great attention to the details of the walking environment will provide important access benefits.

1. The Fort Point Channel setting – The public realm improvements associated with the project are substantial and will take advantage of the waterside site for its many users.

• The project will include a major building entrance facing a widened 18-foot Harborwalk. On the water’s edge overlooks are provided to heighten contact with the Channel and its water views. A seating zone along the Harborwalk is provided as an extension of the central plaza between Brick Buildings and the New Building. We hope that GE will include site programming that takes advantage of the waterfront portion of the site.

• A path network connects the site with the Harborwalk, including accessible paths. It is likely that many pedestrians will use the stairway from Summer Street to the Harborwalk as this is the most direct route between the site and South Station. The route should be well marked with pedestrian wayfinding signs.

• We recommend adding shade trees along the Harborwalk, and amenity that is mentioned quite often in walkers’ comments.

2. Site entrance on Necco Street – Compared with the Harborwalk entrance, the Necco Street entrance design seems less well developed in the EENF. However, this will be the principal entrance to the site for residents arriving from the Fort Point and Seaport Districts, South Boston, and for people driving to the site. Also, Necco Street will of necessity be the route for people with disabilities because the Harborwalk access is via a stairway from Summer Street and the site.
• The Necco Street entrance should be designed to be as important and attractive as the Harborwalk entrance. The sidewalk is shown as widened to 12’, but is narrowed to carve out a lengthy vehicle drop-off lane along much of the site’s frontage. The sidewalk also accommodates the loading zone and garage entries, and bicycle storage on the sidewalk is also suggested. In combination, this mix of service uses would diminish the quality and functionality of the Necco Street sidewalk. We request that the proponent re-examine the sidewalk design to provide a gracious and welcoming entrance along Necco Street.

• Necco Street should be designed as a tree-lined street. In the 100 Acres Plan (2007) that includes this site, Necco Street is proposed to provide walking access to the proposed parkland that extends from the Fort Point Channel to the Boston Convention and Exhibition Center. The street is privately owned, suggesting the possibility for joint action with neighboring properties to improve it. The street right-of-way is nearly 60’ wide which could readily incorporate a design that accommodates two 10-foot travel lanes, two 7-foot parking lanes, and a wide tree-lined sidewalk along the site that also includes
benches and additional landscaping.
• The sidewalk at the main entrance to the buildings should have additional width to accommodate the many potential users. A compelling and elegant front door might be incorporated into the plans for reconfiguring the Brick Buildings.
• A Necco Street crosswalk should be provided at Necco Court to accommodate safe crossing from the large Necco Street Parking Garage across the street.

3. Off-site approaches to the Necco Street site entrance – The existing walking route from Summer Street (and thus South Station) to the boundary of the site is difficult for persons with disabilities to travel. The proponent should take the lead in ensuring that walking improvements are made to this route. This may require significant coordination with the City and with neighboring landowners, but will result in improved access for all users of the neighborhood.

• There is no curb ramp provided from Dorchester Avenue onto the Summer Street Bridge (south/GE side of the bridge). A curb ramp should be provided.

• Accessible access to GE from Summer Street will need to be provided via Melcher Street. However, the sidewalk along the south side of Melcher Street appears appears to have an excessive cross slope that is hazardous for persons with disabilities, and difficult for anyone pushing a stroller or pulling a suitcase. This cross slope will need to be fixed.

• Between Melcher Street and Necco Court on the west side of Necco Street, the sidewalk appears to be 8’ wide, but curb ramps are not provided where driveways cross the street. The sidewalk should be rebuilt to meet ADA requirements and provide a gracious walking route between GE and South Station.

4. Winter weather conditions and general maintenance –

• Management and operations planning should ensure good snow clearance between the site and South Station along the Harborwalk and the sidewalks of Necco and Melcher Streets. The proponent should work with adjacent property owners and business associations to assure good access to its site under winter weather conditions.
• The proponent should explore a greater degree of enclosure and a weather-resistant design for the GE Plaza walkway, a portion of which will be covered by a translucent canopy suspended between Brick Buildings and New Building. The current plan appears to work primarily in warm months, and multi-season use will add interest and vitality to the site.

5. Off-site issues – We urge the proponent to work with the city and the neighboring property owners to bring all nearby pedestrian facilities up to date.

• For example, the sidewalk at the bend of Necco Street (just south of the proponent’s site) needs to be completed, and there are uneven and heaved bricks in the Necco Street sidewalk from the bend to A Street. In addition several areas of the A Street sidewalk toward the Broadway Red Line station are not ADA compliant, because they are too narrow or have missing or insufficient curb ramps.

• The proponent should work with the City to ensure that traffic signal timing works well for pedestrians at intersections near the site.

We appreciate your consideration of our comments and your responses to them, and we look forward to working with GE, the City and other Fort Point community members on this exciting project.

Please feel free to contact WalkBoston with questions you may have.

Sincerely,
Wendy Landman
Executive Director